Posted on: May 31, 2019

2019 Subdivision Paving

Road Construction (1) (002)_edited-1


Red Deer County 2019 Subdivision Paving is scheduled to begin on Monday, June 10. 

This work is weather dependent and the schedule may be subject to change.

Drivers are reminded to slow down and obey all signs when driving in construction zones.

Area:Scheduled to begin:Expected to last:
SpringbrookMonday, June 105.5 days
McKenzie DriveTuesday, June 119.5 days
Green AcresMonday, July 83.5 days
Corner Gate EstatesMonday, July 83 days
Rge Rd 283Tuesday, July 98.5 days
Rge Rd 275 & WaskasooWednesday, July 106.5 days
Westview EstatesThursday, July 118 days
Springvale HeightsFriday, July 128 days
Poplar RidgeTuesday, August 614.5 days
Burnt Lake Trail (night)Friday, August 94 days



If you have any questions about paving or road construction, please call the Red Deer County Office at 403.350.2150.

Facebook Twitter Email

Other News in Red Deer County News

paint can

Joint Waste Roundup

Posted on: June 18, 2019
Capital Projects (1)

Speed Limit Increased

Posted on: June 10, 2019

Red Deer County road bans lifted

Posted on: June 6, 2019